In the example below, the user "Administrator" is working on 2 projects ("IT1367 Delivery Phases" and "Implementation Process56"). The user is assigned to both projects with a total of 110% of their time. This is too much so the Project Manager should change the users assigned to the task. Otherwise, the PM can change the dedicated time or the dates, to make sure that this is feasible.