Translations:Làm thế nào để tính toán các lịch trình điều chuyển?/24/en
Từ Kiu Wiki
Example As an example, you may sell a car today (January 1st), that is purchased on order, and you promise to deliver your customer within 20 days (January 20). In such a scenario, the scheduler may trigger the following events, based on your configuration: - January 19: actual scheduled delivery (1 day of Sales Safety days) - January 18: receive the product from your supplier (1 day of Purchase days) - January 10: deadline to order at your supplier (9 days of supplier delivery lead time) - January 8: trigger a purchase request to your purchase team, since the team need on average 2 days to find the right supplier and order.